About the Annual Roadway Improvement Program
Every year, the City of Newport adopts a seasonal Roadway Improvement Program, which sets out to improve a portion of the roughly 93 miles of local roadways.
Fall 2026 Roadway Improvement Program
Chip Sealing | Repaving
is scheduled to take place on the following streets as part of our annual road improvement program during the week of Sept. 21st
Eustis Avenue from Bliss to Ellery Road
Dana Street from Eustis Avenue
Hazard Street from Eustis Avenue
Michael Terrace
Taber Street from Eustis to Wilbur Avenue
Bliss Mine Road from Ellery Road to Town Line
Barbara Street from Bliss Mine Road to Kay Boulevard
Friend Drive
Kay Street Extension from Bliss Mine Road to Kay Boulevard
Guthrie Street from Bliss Mine Road
Keeher Avenue from Bliss Road to Kay Street
Toppa Boulevard from Bliss Road to Kay Street
Kay Boulevard from Ellery Road to Kay Street
Kay Terrace
Kay Street from Bliss Road to Touro Street
Road Reconstruction
New pavement, along with curbing and sidewalks where applicable, is being installed on the following streets:
Ann Street
Binney Street
Church Street
Cliff Avenue
Cliff Terrace
Colonial Street
Duke Street
Seaview Avenue
Stone Street
Wetmore Avenue
Sidewalk Improvements
Elsewhere, work is also underway along the Kay Street corridor where a multiyear sidewalk improvement project is continuing. Motorists and pedestrians are asked to please be mindful while traversing the area.
Lower Thames Street will see new sidewalks installed in the vicinity of Ann Street as well as new ADA-accessible curb ramps at various points from Memorial Boulevard/America's Cup to Wellington Avenue
The Pine Street Driftway Shoreline Adaptation Project’s final concrete sidewalk panels have been placed.
Roadway & Crosswalk Striping
Roadway pavement line painting takes place annually as warm, dry weather allows.
About the Annual Roadway Improvement Program
Every year, the City of Newport adopts a seasonal Roadway Improvement Program, which sets out to improve a portion of the roughly 93 miles of local roadways.
Fall 2026 Roadway Improvement Program
Chip Sealing | Repaving
is scheduled to take place on the following streets as part of our annual road improvement program during the week of Sept. 21st
Eustis Avenue from Bliss to Ellery Road
Dana Street from Eustis Avenue
Hazard Street from Eustis Avenue
Michael Terrace
Taber Street from Eustis to Wilbur Avenue
Bliss Mine Road from Ellery Road to Town Line
Barbara Street from Bliss Mine Road to Kay Boulevard
Friend Drive
Kay Street Extension from Bliss Mine Road to Kay Boulevard
Guthrie Street from Bliss Mine Road
Keeher Avenue from Bliss Road to Kay Street
Toppa Boulevard from Bliss Road to Kay Street
Kay Boulevard from Ellery Road to Kay Street
Kay Terrace
Kay Street from Bliss Road to Touro Street
Road Reconstruction
New pavement, along with curbing and sidewalks where applicable, is being installed on the following streets:
Ann Street
Binney Street
Church Street
Cliff Avenue
Cliff Terrace
Colonial Street
Duke Street
Seaview Avenue
Stone Street
Wetmore Avenue
Sidewalk Improvements
Elsewhere, work is also underway along the Kay Street corridor where a multiyear sidewalk improvement project is continuing. Motorists and pedestrians are asked to please be mindful while traversing the area.
Lower Thames Street will see new sidewalks installed in the vicinity of Ann Street as well as new ADA-accessible curb ramps at various points from Memorial Boulevard/America's Cup to Wellington Avenue
The Pine Street Driftway Shoreline Adaptation Project’s final concrete sidewalk panels have been placed.
Roadway & Crosswalk Striping
Roadway pavement line painting takes place annually as warm, dry weather allows.
Page last updated: 24 Sep 2026, 08:55 PM
Roadway Paving
Please note that while initial paving work typically moves quickly, sidewalk and curbing improvements require additional time to complete
As with all our projects, access to properties will be maintained with some inconveniences as the roadways are repaved, driveways are replaced and concrete sidewalks poured. Parking may be restricted during the working week as necessary to complete construction.
Pavement Marking Improvements
Every year, pavement markings are repainted throughout the City includin road yellow center line striping, crosswalks, stop bars, and other pavement markings. Because this work requires large areas of the City and negatively impacts traffic flow, the vast majority of the work occurs overnight (8 pm to 6 am). This work is ongoing and paint application is highly weather dependent (e.g., wet streets and cold weather prohibits paint installation).
Questions?
If you have questions or concerns regarding construction happening on your street, please reach out to our Public Services team at www.NewportRI.gov/PublicServices or submit a concern through our ReportIt! Newport portal at www.NewportRI.gov/ReportIt
Thank you for your patience and cooperation while we work to improve our infrastructure.